Saturday, August 22, 2009

Summer Continues



Framing work and plumbing can be seen from this photo. The faux windows are framed in and should be a nice balancing addition to the Church. Some of the piping for the sprinkler system is evident and though you can't tell, electrical work and wiring for the sound system are also in process. There has finally been some progress made outside with the footings for the addition being started. Basement walls could be next week. Let's hope we don't get a repeat of July's rains here in the end of August. Thanks for following along.
Commit your way to God, trust in Him. Ps. 37:5